Motorists will be happy to know, approximately 80% of the South Fork Bridge project, in Front Royal, is complete. It is scheduled for completion in December of this year. The contractor is currently working on stage two, which will widen the structure and provide two additional lanes, a bike lane and sidewalk to the west. The contractor completed setting steel beams and has now begun placing deck forms.

Piers and abutment foundation are complete. Additionally, Curb and gutter stones have been installed on the Service Road along Route 55 and QRI Road.

The service road is likely to be paved later this season when paving companies become more active. Concrete placement of the deck is anticipated for June with completion in early September.

 


,