Leach Run Parkway Project Near Completion

21 March 2017 News


The new Leach Run Parkway project in Front Royal is on track to be completed by June 7, 2017. The final utility relocation work was completed last week along Route 55 (John Marshall Highway) which will allow Branch to complete the widening on Route 55. The contractor is currently finishing up the installation of street lighting as well as landscaping and has crews starting on installation of the bio-retention ponds. Branch is expected to be in position to start work on final paving and pavement markings by early April.

 


, , ,